Kyrgyzstan completes Uch-Kurgan hydropower overhaul, lifts capacity 20%

Kyrgyz power producer Electric Stations has completed a full equipment overhaul at the Uch-Kurgan hydropower plant in the Jalal-Abad region, raising the facility’s installed capacity by 20%, the Energy Ministry said.

With the commissioning of modernized unit No. 1, attended by company chief executive Ulukbek Mamyraliev, all four generating units at the station have now been replaced. The upgrade increased total capacity from 180 megawatts (MW) to 216 MW, representing a 36 MW gain, or an average of 9 MW per unit. The additional output was achieved entirely by installing modern equipment without modifying the dam or reservoir.

During the final phase in 2026, engineering teams and contractors upgraded units No. 1 and No. 2 in parallel. Taking half of the plant’s capacity offline simultaneously required coordinated scheduling and grid dispatch adjustments to prevent power supply disruptions for consumers.

Located on the Naryn River, the Uch-Kurgan plant entered service between 1961 and 1962. Over more than six decades of operation, its main generating equipment had reached the end of its service life, as the facility had previously undergone only routine maintenance without a comprehensive replacement of its units.

According to the Energy Ministry, the expanded capacity and improved reliability of the Naryn River station will support Kyrgyzstan’s power grid ahead of the 2026 to 2027 autumn and winter period, helping the system meet peak seasonal electricity demand.